| Location: | Las Vegas, NV |
|---|---|
| Type(s): | |
| Subtype(s): | |
| Constructed: | 2007-07-16 |
| Completed: | 2008-10 |
| Cost: | $37.5 M |
| Size (sq. ft.): | 112000 |
| Other Size Measure: | Three Story Campus |
| Firm(s): |
|
| Owners: | Clark County School District and Vegas PBS |
| Contractors: | Martin-Harris Construction (General Contractor) |
| Description: | Will house Vegas PBS Studios and offices, the CCSD Virtual High School, and emergency response data casting operations to backup Nevada's Homeland security. Will be applying for LEED Gold Certification |
| Extra Note: | "Nevada News - October 2007." Southwest Contractor. October 2007. [Online]. Available: <http://southwest.construction.com/news/NV/archive/0710.asp>. Accessed October 17, 2007. |